TM 5-6115-640-14&P
b.
Strap Fastener Replacement.
(1)
Remove two screws (5, figure 5-4), flat washers (6), and lock-nuts (7) securing strap fastener (8) to
accessory box (4).
(2)
Position strap fastener (8) on accessory box (4) and install two screws (5), washers (6), and locknuts (7).
Section V. MAINTENANCE OF POWER PLANT TRAILERS
5-9. TRAILER ASSEMBLY REPLACEMENT .
This task covers
1. Removal
2. Installation
Initial Setup:
1.
Tools - General Mechanics Tool Kit (5180-00-177-7033)
2.
Materials/Parts - Trailer Assembly (974U3); 13228E9896 (AN/MJQ-32)
13229E2302 (AN/MJQ-33)
WARNING
When lifting generator set, use lifting equipment with a minimum lifting capacity of 1500 lb. Do
not stand under generator sets while they are being lifted. Failure to observe these precautions
can cause injury or death to personnel or damage to equipment.
The removal and installation procedures for the generator sets are the same for either power plant. The stowage rack
associated with the AN/MJQ-32 may have already have been removed by unit maintenance. If not, refer to paragraph 4-
26 b(1).
a.
Removal.
(1)
Perform generator set Removal procedures given in paragraph 5-5a.
(2)
Remove stowage rack, AN/MJQ-32, if necessary (paragraph 4-26b(1)).
(3)
Remove trailer assembly.
5-10