TM 9-6115-650-14&P
Figure 4-6. Fire Extinguisher Bracket Replacement.
b. Installation.
(1) Position fire extinguisher bracket (4) on fender (5).
(2) Insert four screws (1) with eight flat washers (2) down through bracket (4) and through fender (5).
(3) Install one nut (3) on each screw (1). Tighten hardware to secure bracket (4).
4-21. Leg Prop Assembly Servicing. Servicing of the leg prop assembly is limited to semiannual
lubrication (paragraph 4-9, b.).
Section IX. MAINTENANCE OF ELECTRICAL SYSTEM
4-22. General. This section contains maintenance information on electrical components unique to the power
plant end item. For all other electrical system maintenance, refer to the applicable generator set and trailer
manuals as follows:
a.
Generator Set Maintenance. For generator set maintenance procedures, refer to TM 5-6115-585-12.
b. Trailer Maintenance. For trailer maintenance procedures, refer to TM 9-2330-213-14&P.
4-23. Switch Box Testing. To isolate the source of an electrical system problem, perform continuity tests on
the components of the switch box as described below. Refer to the schematic diagram inside the switch box
(figure 4-7) to locate and identify the test points indicated in these procedures.
a. Power Cable Assembly Test.
(1)
(2)
Set multimeter for continuity testing.
Set switch box rotary switch to GEN 1 position and locate power cable assembly associated with that
switch position.
4-17