TM 9-6115-650-14&P
Table 4-1. Unit Preventive Maintenance Checks and Services (PMCS) (cont).
H - Hours of operation
M - Monthly
S - Semiannually
A - Annually
(As indicated)
(100 hours)
(500 hours)
(1,000 hours)
Interval
Item
no.
H
M
s
A
Item to be inspected
Procedures
25
Wheel Bearings
Clean and repack (page 4-105,
TM 9-2330-213-14&P).
26
Hydraulic Brake Tubes and
Inspect for dents, cracks, loose connections and
Hoses
leaks.
27
Trailer - Road Test
Perform road test paying special attention to items
that were repaired or adjusted.
Section VI. TROUBLESHOOTING
4-13. Troubleshooting. Troubleshooting procedures for components unique to the power plant end item are
given in paragraph 4-14. Troubleshooting information for the individual generator sets and trailer are contained in
their respective technical manuals referenced below.
a. Generator set Troubleshooting. Refer to TM 5-6115-585-12 for troubleshooting procedures applicable to
the generator set.
b. Trailer Troubleshooting. Refer to TM 9-2330-213-14&P for troubleshooting procedures applicable to the
trailer.
4-14. Power Plant Troubleshooting. Table 4-2 contains troubleshooting information for locating and
correcting operating troubles which may develop in components unique to the power plant end item. Each
malfunction is followed by a list of tests or inspections which will help determine probable cause and corrective
actions to take. Perform the tests/inspections and corrective actions in the order listed. This manual cannot list all
malfunctions that may occur, nor all tests or inspections and corrective actions. If a malfunction is not listed or
cannot be corrected by listed corrective actions, notify your supervisor.
4-12