ARMY TM 9-6115-673-13&P
AIR FORCE TO 35C2-3-512-1
b. Column (2) - Interval (Intervals M, Q, S, A, B, H).
These columns tell when to perform a procedure. A dot in a column tells which procedures apply.
Some procedures will have more than one dot.
c. Column (3) - Item To Be Inspected.
This column has the name of the item to be inspected.
d. Column (4) - Procedure.
This column tells how to do the required checks and services.
Carefully perform these
instructions in the order listed.
e. Column (5) - Equipment Is Not Ready/Available If.
This column states conditions that will cause the equipment not to be ready for operation.
4.11. PREVENTIVE MAINTENANCE PROCEDURES.
NOTE
Within designated intervals, these checks are to be performed in the
order listed. If the generator set must be kept in continuous operation,
check and service only those items that can be accessed without
taking the generator set off line. Perform all checks and services
when the generator set can be shut down.
a. Monthly.
Perform monthly (M) PMCS in Table 4-1. Observe WARNINGS and CAUTIONS contained in this
manual and on plates installed on equipment.
b. Quarterly.
Perform quarterly (Q) PMCS in Table 4-1. Observe WARNINGS and CAUTIONS contained in
this manual and on plates installed on equipment.
c.
Semi-annually.
Perform semi-annual (S) PMCS in Table 4-1. Observe WARNINGS and CAUTIONS contained in
this manual and on plates installed on equipment.
d. Annually.
Perform annual (A) PMCS in Table 4-1. Observe WARNINGS and CAUTIONS contained in this
manual and on plates installed on equipment.
e. Bi-annually.
Perform bi-annual (B) PMCS in Table 4-1. Observe WARNINGS and CAUTIONS contained in
this manual and on plates installed on equipment.