TM 9-6115-669-13&P
d.
e.
f.
g.
h.
i.
j.
k.
l.
NOTE
Description of installation of power cable at EPP III end.
For all parts, note installation position (conical).
Cut cable (9) to a length of 95.12 ft (29 m). Strip cable conductors and shield at both ends.
At EPP III socket end, pull heat shrink tubing (6) with 5.19 x 2.36 inch (132 x 60 mm) rubber
flap (7) over cable.
Unscrew EPP III plug (1) with all parts.
Solder parts (11) and (12) to cable conductors (see table 6-2).
Pull parts (23, 22, 21, 20, 19) over cable, in that order.
Pull cold shrink tubing (4) over cable so that draw cord faces toward the cable.
Pull parts (18, 17, 16, 16, 14) over cable, in that order.
Insert pins (11) and (12) into part (13) as shown in table 6-2. Note installation position.
Slide part (14) onto part (13).
m. Place part (16) into part (14).
n. Slide part (16) into part (14) and screw onto part (13).
o.
Place cable shield over part (16) and press onto part (17).
p.
Slide part (18) over part (17) and screw onto part (16).
q.
Slide cold shrink sleeve onto part (18) and pull drawcord backward. This places the sleeve over
the cable.
r.
Screw parts (19) and (16) together.
s.
Place part (20) in part (19).
t.
Slide part (21) into part (19).
u. Slide part (22) into part (19).
v.
Screw parts (23) and (19) together.
w. Install hose clamp (3).
x.
Shrink heat shrink tubing (2) over hose clamp (3).
y.
Position two heat shrink tubing-s (6) with labels (8).
z.
Position heat shrink tubing (6) with 5.19 x 2.36 inch (132 x 60 mm) rubber flap (7) on EPP III
plug end.
aa. Assemble ECS plug end in the same procedure as EPP III end.
ab. Test cable as indicated in steps above.
5-22