5. Connect coolant hose (Figure 1, Item 13) to bottom of heater (Figure 1, Item 6) and install hose clamp (Figure
1, Item 12).
6. Connect 90-degree elbow coolant hose (Figure 1, Item 11) to top of heater (Figure 1, Item 6) and install hose
clamp (Figure 1, Item 10).
7. Connect generator set wiring harness (Figure 1, Item 9) to heater (Figure 1, Item 6) in two places.
8. Connect flexible braided leak-off hose (Figure 1, Item 8) to OUT side of fuel metering pump (Figure 1, Item 5)
and install hose clamp (Figure 1, Item 7).
9. Connect low-pressure hose (Figure 1, Item 4), hose clamp (Figure 1, Item 3) and fuel metering pump (Figure
1, Item 5) to inside of fuel pump (Figure 1, Item 6)
10. Open shutoff valves (Figure 1, Item 1) and (Figure 1, Item 2).
WARNING
Operating the generator set with any access door open exposes personnel to a high noise level.
Hearing protection must be worn when operating or working near the generator set with any
access door open. Failure to comply can cause hearing damage to personnel.
11. Operate engine and check for leaks.
12. Close right and left battery access doors and right front doors.