4. Install control box cover (Figure 1, Item 21) on control box frame (Figure 1, Item 9) with two screws (Figure 1,
Item 20).
5. Install toggle switch (Figure 1, Item 19) on control box faceplate (Figure 1, Item 8) with jam nut and
lockwasher (Figure 1, Item 18).
6. Install circuit breaker (Figure 1, Item 17) on control box faceplate (Figure 1, Item 8) with jam nut and
lockwasher (Figure 1, Item 16).
7. Install press-test indicator light (Figure 1, Item 15) and install jam nut and lockwasher (Figure 1, Item 14) on
control box faceplate (Figure 1, Item 8),
8. Install LED holder (Figure 1, Item 13) on control box faceplate (Figure 1, Item 9) and install jam nut and
lockwasher (Figure 1, Item 12) and collar (Figure 1, Item 11).
9. Install control box faceplate (Figure 1, Item 9) and control box mounting bracket (Figure 1, Item 8) on control
box frame (Figure 1, Item 10) with two screws (Figure 1, Item 7).
END OF TASK
INSTALLATION
1. Install winterization heater control box assembly (Figure 1, Item 6) on rear of generator housing and secure
with two washers (Figure 1, Item 5), lockwashers (Figure 1, Item 4), and screws (Figure 1, Item 3).
2. Connect connector P27 to connector J27 (Figure 1, Item 2) and connector P26 to connector J26 (Figure 1,
Item 1).
3. Close left rear doors.
END OF TASK
END OF WORK PACKAGE
0089-4