NOTE
positions.
(3) Check for open circuits between terminals COM and NO, and terminals A and B.
(4) Place and hold ON-OFF load circuit breaker assembly in ON position.
(5) Check for continuity between terminals COM and NO, and terminals A and B.
(6) Remove shrink wrap and check diode assembly CR2 as follows:
leads and note resistance.
(b) Resistance should be high in one direction and low in the other. If resistance
is high or low in both directions, replace entire ON-OFF load circuit breaker
assembly.
(7) Remove and replace entire assembly if any continuity/resistance check is other
than indicated above.
(8) Close and secure instrument panel.
c.
Testing. (MEP-501A)
(2) Release instrument panel by turning fastener, open instrument panel slowly.
NOTE
positions.
(3) Set multimeter to ohms and with ON-OFF load circuit breaker assembly in ON
position, check for continuity between terminals P1 and P2.
(4) Check for open circuit between terminals P1 and P2 with load circuit breaker in
OFF position.
(5) Repeat steps (3) and (4) for other half of ON-OFF load circuit breaker.
(6) Remove and replace entire ON-OFF load circuit breaker if any reading is other
than indicated above.
(7) Close and secure instrument panel.