5.17 CONNECTION PANEL MAINTENANCE.
This task covers:
a.
d.
Removal
b.
Inspection
c.
Test
Repair
e.
Installation
INITIAL SETUP
Tools
General Mechanics Tool Kit
(item 2, appendix B)
Automotive Fuel and Electrical System Repair, Tool
Kit (item 3, appendix B)
Equipment Conditions
Reference
Shut down Generator Set
150 kW, paragraph 2.8.1.
Removal tool 1 (item 20, appendix B)
Removal tool 2 (item 21, appendix B)
Materials/Parts
Cable ties (item 2, appendix E)
Solder (item 7, appendix E)
Personnel Required
TWO
WARNING
l The Generator Sets 150 kW produce lethal voltages.
l Turn off power to the EPP III or Generator Set 150 kW before
performing any installation, removal, disassembly, or
assembly work.
l Wear protective gloves when performing any work on main
assemblies of the EPP III.
CAUTION
Label all cables before removing electrical or electronic assemblies or
components.
a.
Remove stanchion by PDU (1, figure 5-20).
b.
Open access door (2) and secure with prop (3).
c. Install stanchion.
5-53