Replace damaged door seals (71)
f .
Replace all damaged sound insulation (69) and missing clip halves (68). If necessary, refer to Appendix
D to make sound unsulation.
2-20.4. Installation.
a. Install center housing panel (62, FIGURE 2-9) on generator set with bolts (61), washers (60),
lockwashers (59), and nuts (58).
b
Secure output box assembly to center housing panel (62) with bolts (52) and (56), nuts (55) and (57),
washer (53). and spacer (54).
c.
Install stiffener (51) on side panel (23) with bolts (47), washers (50), lockwashers (49), and nuts (48).
d.
If removed, install sound insulation (69) on deflectors (46) and (31) and clip halves (68).
e.
Install deflector (46) on side panel (23) with bolts (43), lockwashers (44), and washers (45).
f.
Install power cable clamp (75) onto deflector (46) with bolt (72), washer (73), and nut (74).
g.
Install frequency control cable box (42) on side panel (23) with bolts (40) and nuts (41).
h.
If removed, install sleeve (67), ring (66), gasket (65), nuts (63), and bolts (64) to load entrance box (39).
i .
Install load entrance box assembly (39) on side panel (23) with bolts (37) and nuts (38).
j.
Install stiffener (36) on side panel (24) with bolts (32), washers (35), lockwashers (34). and nuts (33).
k.
Install deflector (31) on side panel (24) with bolts (28), lockwashers (29), and washers (30).
I.
Install slave receptacle box (27) on side panel (24) with bolts (25) and nuts (26).
m.
Install rear side panels (23) and (24) on generator set with bolts (20), lockwashers (21), and washers
(22).
n.
Install bolts (18) and nuts (19), to secure rear side panels (23) and (24) to center housing panel (62).
o.
Install rear lifting ring brackets (16) and lifting rings (17) on skid with bolts (12), washers (15),
lockwashers (14), and nuts (13).
p.
Install lower door sill (11) with bolts (7), washers (10), lockwashers (9), and nuts (8)
q.
Install center door post (6) with bolts (4) and nuts (5).
r .
Install upper door sill (3) with bolts (1) and nuts (2).
s.
Install load terminal board upper mounting bracket, paragraph
t.
Install air cleaner assembly, paragraph 2-67.4
u.
Install frequency adjust control cable assembly, paragraph 2-89.3.
v.
Install NATO SLAVE RECEPTACLE, paragraph 2-13.3.
w.
Install low oil pressure switch, paragraph 2-90.4.
x.
Install oil pressure sender, paragraph 2-91.4 and oil line (3, FIGURE 2-25) at engine fitting,
y.
Install DEAD CRANK switch, paragraph 2-96.4.
z.
Install engine access doors, paragraph 2-15.4.
aa. Install top housing panel, paragraph 2-17.4.
ab. Install load terminal and storage box access doors, paragraph 2-15.4
ac. Install control box assembly, paragraph 2-21.4
ad. Connect negative battery cable and close all access doors.