TM 5-6115-628-14&P
(3) Insert three screws (1) down through trailer frame (5) into accessory box (4).
(4) Install one nut (3) and one washer (2) on each screw (1) and tighten.
4-20.
Fire Extinguisher Bracket Replacement. (See figure 4-7.) The fire extinguishers supplied with
the power plant are carried in brackets mounted on the front roadside steps of the trailers.
a. Removal.
(1) Remove four screws (1, figure 4-7), four flat washers (2), and four nuts (3) securing
bracket (4) to step (5).
(2) Remove bracket (4) from step (5).
b. Installation.
(1) Position fire extinguisher bracket (4) on step (5).
(2) Insert four screws (1) down through bracket (4) and through step (5).
(3) Install one washer (2) and one nut (3) on each screw (1). Tighten hardware to secure
bracket (4).
Figure 4-7. Fire Extinguisher Bracket Replacement.
4-21.
Front Steps Replacement. (See figure 4-8.) The roadside and curbside front steps on both
trailers are symmetrical, and replacement procedures are the same except where noted in the steps
below.
a. Removal.
NOTE
When removing roadside front step, omit steps (1) and (2).
(1) Remove fuel can brackets (paragraph 4-18, a).
(2) Remove accessory box (paragraph 4-19, a).
4-18