Figure 5-4.
TM 5-6115-625-14&P
(1)
(2)
(3)
(4)
(5)
(6)
5-4
Attach lifting equipment with a minimum lifting capacity of 3500 lb (1, figure 5-4) to lifting
eyes (2) on top edges of generator set (3). Insert a rope (4) through each of four tiedown
rings (5) on generator set.
With one person at each rope to steady and guide generator set (3), lift generator set and
carefully lower it onto trailer.
N O T E
Two center mounting screws on each side can be reached through cutouts in
trailer frame under each fender.
Insert eight screws (4, figure 5-3) with beveled washers (5) down through generator set
skids into trailer.
Working under trailer install one flat washer (6) and one nut (7) on each
screw (4).
Position beveled washers (5) so that screw heads are parallel to tops of washers. While
holding beveled washers in position, tighten hardware.
Connect generator set ground wire (1) to trailer GROUND TERMINAL stud (3).