CHAPTER
TEST AND INSPECTION
TM 5-6115-625-14&P
6
AFTER REPAIR
Section I. GENERAL REQUIREMENTS
6-1.
General Requirements. The activity performing the repair is responsible for the performance of
all applicable tests and inspections specified in the technical manuals referenced below. Activities
performing maintenance on any component of the power unit must perform those tests and inspections
required by the applicable component or system repair instruction.
Section Il. INSPECTION
6-2. Generator Set Inspections. Refer to TM 5-6115-464-12 and -34 for inspections required
following repair of the generator set.
6-3. Trailer Inspections. Refer to TM 9-2330-205-14&P for inspections required folIowing repair of
the trailer.
Section Ill. OPERATIONAL TESTS
6-4. Generator Set Operational Tests. Refer to TM 5-6115-464-12 and -34 for operational tests
required to verify satisfactory performance of the generator set.
6-5. Trailer Operational Tests. Refer to TM 9-2330-205-14 for operational tests required to verify
satisfactory performance of the trailer.
6-1/(6-2 blank)