TM 9-6150-226-13
system for use with single-phase input power originating from the single-phase
smaller kilowatt rated generator sets, generally a 5KW generator.
(1) You will have to determine the number, type and location of the
40 amp or 60 amp distribution systems needed.
Table 2-3.
EXAMPLE OF DETERMINING USER NEEDS
Required Receptacle
Totals
Total
120 V/1-ph
208 V/3-ph
Kilowatts
Amps
MIL STD/Univ.
Area
Item
Plug(s)
Adapter
1-ph
3-ph
Tent #1
1.) Electric drill 120 V/800W
1
.800
6.6
2.) Electric grinder 120 V/7.5 amps
1
.900
7.5
3.) Sander 120 V/450W
1
.450
3.75
4.) Radio set 120 V/180W
1
.180
1.5
5.) Lights 120 V/60W ea
6
.360
3.0
6.) Welder 208 V/1 1/2HP/4.5 amps
1
1.500
4.5
TOTAL FOR TENT #1
10
1
4.190
22.35
4.5
Tent #2
1.) Electric heater 120 V/10.8 amps
1
1.300
10.8
2.) Radio transceiver 120 V/1000W
1
1.000
8.3
3.) Light set 120 V.60W ea
1
.360
3.0
TOTAL FOR TENT #2
3
2.660
22.1
Tent #3
1.) X-Ray unit 120 V/5 amps
1
.600
5.0
2.) Film processor 120 V/120W
1
.120
1.0
3.) Suction unit 120 V/140W
1
.140
1.2
4.) Prophylaxis unit 120 V/1500W
1
.150
1.3
5.) Surgery lamp 120 V/10 amps
1
1.200
10.0
6.) Light set 120 V/60W ea
1
.
.480
4.0
TOTAL FOR TENT #3
6
2.690
22.5
TOTAL REQUIREMENTS
19
1
9.540 66.95 4.5
(2) When using the 40-amp distribution system, determine the number and
location of 100-amp and/or 200-amp feeder systems, if any.
(It is more efficient to
locate the power consuming equipment as close to the power source as possible, thereby
minimizing the need for feeder systems).
Refer to Table 1-4 for pairing of the 40-amp
distribution system to the appropriate sized generator.
2-31