TM 9-6115-730-24
0041
INSTALLATION
1. Install control box panel assembly (Figure 1, Sheet 1, Item 4) on control box (Figure 1, Sheet 1, Item 8) and
hook holder (Figure 1, Sheet 3, Item 7) to control box.
NOTE
Remove tags and connect wiring as required.
2. Raise control box panel assembly (Figure 1, Sheet 1, Item 4) and secure three studs (Figure 1, Sheet 1,
Item 3).
3. Close control box door (Figure 1, Sheet 1, Item 2), and turn two latches (Figure 1, Sheet 1, Item 1) to secure.
4. Restore power by setting DEAD CRANK SWITCH to NORMAL, Battery Disconnect Switch ON, and ENGINE
CONTROL switch to OFF/RESET.
5. If GSC has been removed and installed, reprogram to restore required generator set values and parameters
END OF TASK
END OF WORK PACKAGE
0041-11/12 blank