(8)
Replace current transformer if multimeter indication in any phase is other than stated in step (5).
(9)
Remove current transformer from test circuit.
(10) Install current transformer, refer to paragraph 5.8.4.c.
c. Installation.
(1)
Install current transformer (4, Figure 5-4), washers (3), screws (2), and locknuts (1) on rear
panel (33).
(2)
Install main generator cables on current transformer (4) and droop current transformer (7) the
same number of wraps recorded during removal.
(3)
Connect main generator cables T2 and T8 to voltage reconnection board (34). Remove tags.
(4)
Connect electrical leads to current transformer (4). Remove tags.
(5)
Install output box top panel, paragraph 5.8.1.
(6)
Install DCS control box assembly, paragraph 4.8.1.
(7)
Close output box and engine compartment access doors.
(8)
Connect negative battery cable to battery, and close BATTERY ACCESS door.
5.8.5
Droop Current Transformer CT5.
a. Removal.
(1)
Shut down generator set, paragraph 2.11.2.
(2)
Open BATTERY ACCESS door (Figure 1-2), and disconnect negative battery cable.
(3)
Open output box and right side engine compartment access doors (Figure 1-2).
(4)
Tag and disconnect main generator cables T2 and T8 from voltage reconnection board (34,
Figure 5-4).
NOTE
Record number and direction of wraps when removing main generator cables
from transformer for installation later.
(5)
Unwrap main generator cables from droop current transformer (7).
(6)
Tag and disconnect droop current transformer (7) electrical leads from terminal board (35).
(7)
Remove locknuts (5), screws (6), and droop current transformer (7) from rear panel (33).