TM 9-6115-670-14&P
5-69
p. Using lifting device, lift generator (19) off generator mount (20) and set down on firm, flat
surface.
q. Using lifting device, align studs (12) on bell housing (17) and holes in generator coupling (18)
and install generator (19) to engine.
r. Secure generator (19) to mount (20) with hex-head screws, lock washers and spacers (21).
Torque between 29 and 34 ft-lbs (39.4 and 46.2 Nm).
s. Reach inside generator air vent and secure generator coupling to bell housing by installing four
nuts and lock washers (11) on four studs (12).
t. On generator exterior, secure generator coupling (18) to bell housing (17) by installing four
socket head screws and lock washers (16) (two on top and two on bottom).
u. Secure generator to flywheel adaptor (13) with six bolts and lock washers (7). Torque between
28.9 and 33.3 ft-lbs (39.2 and 45.1 Nm).
v. Install two generator grids (13) and air deflectors (9) and secure with eight bolts and lock
washers (10).
w. Remove lifting device.
x. Install two bolts (7, Figure 5-13) (JTACS) and lock washers (6), or three bolts (SICPS and WIN-
T), flat and lock washers, to regulator box, (1) and secure to generator housing.
WARNINGS
A heavy lifting device and two personnel are
required to lift the diesel engine on and off the
frame. DO NOT use a lifting device with lifting
capacity of less than 500 pounds (226.8 KG).
DO NOT stand or sit on the 10 kW generator as it
is being hoisted, lowered, or transported.
DO NOT lift the 10 kW generator over personnel.
When using lift ring, ensure that a closed ring with
safety latch is used. NO OPEN HOOKS are to be
used when lifting 10 kW generator.
Lift ring must have a swivel attached to prevent
equipment from swinging.
Hard hats must be worn when 10 kW generator is
removed by overhead lift ring.
Failure to observe these warnings could result in
severe injury to personnel or DEATH.
NOTE
Ensure ground wire and electrical leads are installed in
the same place.