TM 9-6115-669-13&P
NOTE
The rail posts and chain assemblies are of different length which
dictates their position.
j.
Put all safety rail posts and chains with clips on the walkway. Install the safety rail posts (4,5)
as follows:
1.
Individual posts with two lengths of chain attached to each, are placed into the first four
post positions (holes) in the walkway on each side of the truck (starting from the front),
with the loops on the posts facing away from the EPP III. Connect each post to the next
one with the chains and clips.
2.
Starting at one corner of the walkway (fifth post position), on either side of the truck, place
a set of 3 posts with four lengths of chain (6) into both corner post positions and one rear
position. Repeat this for the other side of the truck with the loops on the posts facing away
from the EPP III.
3.
Connect the loose safety rail chains on either side of the truck to the next post rearward.
Install the 2 remaining lengths of chain between the two middle safety rail posts on the
tailgate section of the walkway.
k.
Return to the ground and place the small pins (see step f.) through the base of their respective
safety rail posts.
l.
Remove the four black exhaust extensions from their compartment (14). Attach the extensions
to the Generator Set 150 kW exhausts by sliding the end of the extension over the exhaust
outlet (15) and twisting the extension to the left (counter clockwise) until it locks in place.
WARNING
Do not use leaky exhaust hoses. Keep exhaust hoses away from
flammablematerials.
When operating indoors, provide adequate ventilation.
CAUTION
Do not block the Generator Set 150 kW air intake and discharge openings.
Make sure intake air is as cool as possible. Hot intake air will cause engine
overheating. Drawing hot air into the air filter will lead to reduced power
output.
NOTE
The EPP III is now in its operational configuration.
2 - 3 3