TM 9-6115-669-13&P
Table 2-9 Electric Power Plant III, Operator Preventive Maintenance Ckecks and Service
(PMCS). -continued
Item
Number
9
10
11
12
13
14
15
16
Interval
During
During
During
During
After
After
After
After
Location
Item to Check/Service
PDU
Grounding
Power Cables
Control Cables
Pallet Frame
Support Arms, Walk-
ways, Chains, Stan-
chions and Comer Pan-
els
PDU Control Cabinet
Power Cable Peels
Procedure
Check lights, gauges, and indi-
cators.
Check all grounds.
Check cables for functionality
Check cables for functionality
Pallet must be secure to truck
chassis.
Check:
Support Arms, Walkways,
Chains, Stanchions must be se-
cure.
Check:
Cabinet is in place and secure.
Electrical connections are ac-
complished. Shock absorbers
are secure and all controls and
indicators are in place and se-
cure.
Check for loose or missing hard-
ware and operation of swing
mounts ratchet and release
mechanisms.
Not Fully Mission
Capable if:
Lights are not working,
indicators and gauges
are not functioning.
Loose or missing hard-
ware.
Ground cables are not
attached. Loosen, bro-
ken or missing hard-
ware.
Power cables are not
functional or are cut or
sliced.
Control cables will not
function or is cut or
sliced.
Pallet frame is not se-
cure to truck chassis.
Loose broken or missing
hardware.
Support Arms and
Walkways are not se-
cure, comers are miss-
ing. Chains and Stan-
chions are not in place,
loose broken or missing
hardware.
Cabinet is not secure,
electrical connections
are not connected or se-
cure. Shock absorbers
are not secure, indica-
tors and controls are not
present or secure. Loose
or missing hardware,
knobs or switches.
Swing mounts will not
swing. Reels will not al-
low cable to be un-
reeled. Ratchet releases
will not operate or loose
or missing hardware.