TM 9-6115-669-13&P
Section III. MAINTENANCE PROCEDURES
5.5 GENERAL.
This section will provide authorized unit level maintenance instructions for EPP III and its
components. Each major component will be covered under its own paragraph heading. Each
paragraph will be further divided into specific maintenance tasks, as directed by the Maintenance
Allocation Chart (MAC). These tasks will include inspection on unit level, removal and installation,
as applicable. Step by step instructions and spot illustrations will guide personnel through each
maintenance task.
WARNING
Potential 150/208 VAC kw shock hazard with failure to adhere to this
warning. Contact with this high power could result in death or
severe injury. If the removal of one generator from the EPP III is
required, replace it with an extra generator if available. If the EPP
III must be operated with only one generator installed, insure that
all cables for the removed generator have the protective caps
properly installed prior to starting the remaining generator set.
Prior to energizing the equipment the operator must check for
exposed electrical terminals.
Always install protective covers on control and power cables when
cables are not connected.
Be sure to observe all Warning labels on equipment.
Potential 208 VAC shock hazard. Do not disconnect or connect
control or power cables while generator set 1 or 2 is running.
WARNING
The Generator Sets 160 kW produce lethal voltages.
Turn off power to the EPP ID or Generator Set 150 kW before
performing any installation, removal, disassembly, or
assembly work,
Wear protective gloves when performing any work on main
assemblies of the EPP III.
CAUTION
Label all cables before removing electrical or electronic assemblies or
components.
N O T E
Secure all screws and nuts (except those on electrical connections) with
Loctite 243.