TM 9-6115-669-13&P
N O T E
Power cable drum (4) has one beveled edge. Rotate the cable drum so
the beveled edge is at the top; this will allow to open the front panel
(13) of the Generator Set 150 kW.
b.
Detach all cables from connector panel (5), as follows:
Disconnect control cable as follows:
(1) Unscrew protective caps (7, 8) from one another.
(2) Pull control cable (6) out of J9 PARALLEL OPERATION socket.
(3) Screw protective cap (8) onto plug at end of control cable (6).
(4) Screw protective cap (7) onto J9 PARALLEL OPERATION socket.
Disconnect power cables as follows:
(1) Disconnect plug (12) and pull power cable L1 out of L1 (OA) socket and install
protective cover (18) on cable end.
(2) Disconnect plugs (9, 10, 11) and pull out power cables L2 (OB), L3 (OC) and N and
install protective covers (15, 16, 17) on cable end.
c.
Remove the four Generator Set 150 kW mounts:
(1) Remove nut (1, figure 4-21).
(2) Unscrew nut (2) to end of threads.
(3) Swing plate (4) with bolts (5) in the direction of the arrow.
(4) Screw nut (2) down and screw nut (1) back on temporarily.
d.
Detach grounding straps from Generator Set 150 kW
(1) Remove nut (6), serrated lock washer (7), washer (8), and grounding strap (9) from
grounding bolt (13), and leave washer (14) on grounding bolt (13).
(2) Put washer (8) and serrated lock washer (7) back on, and screw nut (6) on temporarily.
e.
Remove exhaust hose (12) and stow.
f.
Swing cable drums into stowed position and lock in place.
CAUTION
Use only a crane with a capacity of approximately 12,000 lb. (6 metric
tons).
g.
Remove sling assembly (2, figure 4-22) from pallet frame (3). Suspend sling assembly on crane,
and position crane approximately over the center of the Generator Set 150 kW (1), as shown in
figure 4-22.
4-46
Change 1