TM 9-6115-669-13&P
2.7 OPERATING PROCEDURES.
When operating the EPP III ensure all personnel are wearing
hearing protection. Failure to observe this warning could
result in severe personal injury due to loss of hearing.
Do not operate the generator sets unless all grounding
provisions are properly and securely connected Electrical
faults in the generator sets, load lines, or load equipment can
cause severe personal injury or electrocution from contact
with the ungrounded system.
If operating the EPP III with only one generator set
installed, insure that all cables for the missing generator set
have protective covers installed prior to starting the
remaining generator set.
Potential 208 VAC shock hazard. Do not disconnect or
connect control or power cables while generator set 1 or 2 is
running.
Always install protective covers on control and power cables
when cables are disconnected.
CAUTION
Before operating the generator sets, check the voltage and frequency
requirements of the load against the voltage and frequency rating of
the generator sets. If the voltage and frequency requirements do not
match the generator sets ratings, DC NOT attempt to operate the
generator sets.
When they are deployed, cables and exhaust extensions lie on the
walkway and create a hazard to walking. Care should be exercised
when on the walkways to avoid falls and possible injury.
2.7.1 General operating procedure.
CAUTION
All Generator Sets 150 kW PMCS must be accomplished prior to starting
the engine (refer to TM 9-6115-668-13).
All operations are controlled from the control panels (1 to 3, figure 2-17):
Switch on the generator sets at control panel (1).
Activate the RS and ECS loads at control panel (3).
Perform switching operations and observe operations at control panels (1 to 3).
The general operating procedure is described in table 2-10.
2 - 4 8
Change 1