TM 9-6115-669-13&P
Table 2-10 General Operating Procedure.
SETTING UP
1.
Set up EPP III equipment for operational configuration.
2.
Connect cables to RS and ECS loads for appropriate operating mode, including
grounding (voltage compensation/lightning protection).
3.
Generator sets:
Check Oil level
Check Fuel level
STARTING UP
1.
Switch on generator sets.
2.
Activate ECS and/or RS loads.
OPERATION
1.
Monitoring during operation.
Observe generator instruments indicating total power and power distribution of
phase conductors and loads.
Paragraph
2.6.1
2.6.2
2.6.3
2.6.4
2.7.2
2.7.3
2.7.4
If necessary, use parallel mode to divide power.
To cool off generator, switch to idle or shut down.
Each generator can individually generate full power.
2.
Generator activation/changeover.
Start up additional generator.
Adjust voltage and frequency on generator control panel.
Push button to switch to parallel operation on generator or PDU control panel
(for converter changeover) Changeover proceeds automatically.
3.
Battle Short function.
Can be implemented from ECS or Generator Set 150 kW control panel.
4.
Emergency shutdown.
If fault or short circuit occurs, immediately switch generator to idle from ECS.
SHUT-DOWN
1.
While generator is running, disconnect loads by selecting ECS off/RS off in ECS.
2.
Shut down generator at generator control panel: normal, or emergency under load.
TAKE DOWN
1.
Convert EPP III to road travel configuration.
2.7.5.1
2.7.5.2 to
2.7.5.5
2.7.5.7
2.7.5.6
2.8.1
2.8.2
2-50