TM 9-6115-646-14&P
4-2.
Installation. (See figure 4-3 ) Installation of the power unit at a worksite involves positioning the trailer and
grounding the power unit.
a.
Positioning Power Unit. Position the power unit on the work-site as follows
(1)
Select an area as level as possible to install power unit and position trailer
(2)
Set trailer handbrakes and lower swivel casters
(3)
Level trailer by turning handwheel on either or both swivel casters
(4)
Chock trailer wheels
CAUTION
Remove fire extinguishers from power unit when generator set Is in operation This will insure that, in the
event of fire, the extinguisher will remain accessible
(5)
Locate fire extinguisher on ground away from power unit
Figure 4-3. Installing Power Unit.
4-4