c.
Rotate both
FREQUENCY adjust
potentiometers to
obtain the same
frequency indication
on both sets.
Ensure load
contactor at load is
open.
d.
Position and hold AC
CIRCUIT INTERRUPTER
switch, on generator
set No. 1, to CLOSED
until indicator
lights.
e.
Place the UNIT-
PARALLEL switch on
both units in
PARALLEL position.
CAUTION
If synchronizing
lights on
generator set
No. 2 do not
glow bright and
dark in unison,
the phasing is
wrong.
Shut
down generator
sets and check
that load cables
are connected
properly.
Failure to
observe this
caution can
result in damage
to generator
sets.
f.
Observe synchroni-
zing lights on
generator set No. 2.
The lights should be
glowing bright and
dark in unison.
ARMY TM 9-6115-645-10
AIR FORCE TO 35C2-3-444-11
MARINE CORPS TM 09244A/09245A-10/1
g.
Adjust frequency of
generator set No. 2
until synchronizing
lights glow bright
and dark in unison
at 2 to 3 second
internals.
CAUTION
Check that load
contactor at
load is open
before attempt-
ing to place
generators on
the line.
Failure to
observe this
caution can
result in damage
to generator
sets.
h.
When both
synchronizing lights
are dark, position
and hold AC CIRCUIT
INTERRUPTER switch
of generator set No.
2 to the CLOSED
position until
indicator lights.
NOTE
The generator
sets are now
operating in
parallel with no
load.
i.
Rotate FREQUENCY
adjust potentio-
meter of generator
set No. 1 until
kilowattmeter
(PERCENT POWER)
indicates
approximately O.
2-27