ARMY TM 9-6115-644-24
AIR FORCE TO 35C2-3-446-12
MARINE CORPS TM 09249A/09246A-24/2
k. Install bolt (1), flatwasher (3), Iockwasher (4), and nut (2) securing ground strap (15) to skid base.
l.
Install bracket (38), wrench (37), and cord (36) on support (33) with bolts (35) and nuts (34).
m. Install generator set housing rear panel, paragraph 2-18-4.
n. Connect load output cables L1, L2, L3, and L0 at load output terminal board and close Ioad terminal access door.
o.
Connect negative battery cable. Close battery access door.
2-104 LOAD OUTPUT TERMINALS
2-104-1 REMOVAL.
a.
Shut down generator set.
b. Open battery access door and disconnect negative battery cable.
c. Open load terminal board access door and disconnect load cables.
d. Remove load output terminal board assembly from generator set, paragraph 2-103-1.
e. Remove nuts (20, FIGURE 2-29), copper washers (21), and load terminals (23) from terminal board assembly
(12).
2-104-2 Inspection
a. Shut down generator set.
b. Open load terminal board access door.
c. Inspect load terminals for stripped threads or other obvious damage.
d. Replace damaged load terminals as necessary.
e. Close load terminal board access door.
2-104-3
Installation.
a.
Install load output terminals (23, FIGURE 2-29) on load output terminal board assembly (12) with copper wash-
ers (21 ) and nuts (20).
NOTE
Ensure GND load terminal passes through ground plane bracket (29) and LO load
terminal passes through bus bar (22).
b. Install load output terminal board assembly in generator set, paragraph 2-103-4.
c. Connect load cables and close load terminal board access door.
d. Connect negative battery cable and close battery access door.
2-148