c. Inspection.
(1)
Remove batteries, step b.
(2)
Inspect batteries (1 and 9, Figure 4-3) for cracked cases; broken, burned, or corroded posts; missing
parts; and other damage.
(3)
Install batteries, step e.
d. Service.
(1)
Remove terminal covers (2, Figure 4-3) from batteries (1 and 9).
(2)
Clean terminal lugs (4, 5, 6, and 7) and battery posts.
(3)
Install terminal covers (2) on batteries (1 and 9).
e. Installation.
(1)
Slide battery horizontally into battery adapter (15) with negative battery post first, until adapter lock
snaps into the lock position.
(2)
Position batteries (1 and 9, Figure 4-3) in battery tray (14) with positive post toward the generator
set. Ensure batteries are serviced and fully charged.
(3)
Apply general purpose grease (Item 10, Appendix E) to battery posts and terminal lugs (4, 5, 6, and
7).
(4)
Secure batteries (1 and 9) to battery tray with battery holddown rods (13), battery holddown
assembly (12), washers (11), and nuts (10).
CAUTION
Interconnect battery cable terminals are marked with positive and negative.
Ensure the cable is installed properly. Failure to comply can cause damage to
equipment.
(5)
Connect positive battery cable terminal lug (7) to battery (9).
(6)
Connect interconnect battery cable terminal lug (5) first, then leg (6) to batteries (1 and 9).
(7)
Connect negative battery cable terminal lug (4) to battery (9).
(8)
Close BATTERY ACCESS door.
4.6.4
NATO SLAVE RECEPTACLE.
a. Inspection.
(1)
Shut down generator set, paragraph 2.11.2.
(2)
Open BATTERY ACCESS door (Figure 1-2).