TM 9-6115-669-13&P
1.
2.
3.
4.
5.
6.
7.
Set MASTER LOAD switch on load bank to OFF.
Open AC Circuit Interrupter on generator set.
After a 30-second cool down, turn BLOWER/CONTROL POWER switch on load bank to OFF.
Set all remaining switches on the load bank to OFF.
Set all switches on the EPP-III/EPU junction box to OFF.
Shut down generator set.
Disconnect load bank cables L1, L2, L3, LO and generator power and control cables from EPP
III/EPU junction box. Disconnect all ground cables.
4-114
Change 1