ARMY TM 9-6115-645-10
AIR FORCE TO 35 C2-3-444-11
MARINE CORPS TM 09244A/09245A-10/1
2-5.5 The Equipment is not ready/availtable if". This
column tells you when and why the generator set cannot
be used.
Equipment operation is allowable with minor
oil and coolant leakage (Class I or II).
Of course, you must consider the fluid capacity
in the item/system being checked/inspected.
When in doubt, notify the next higher level of
maintenance.
When operating with Class I or Class II leaks,
continue to check fluid levels as required in
your PMCS. All leaks should be reported to the
next higher level of maintenance.
2-5.4 Procedures Column The procedures column of
your PMCS table tells you how to do the required checks
and services. Carefully follow these instructions. If you
do not have the tools, or if the procedures indicate, com-
plete a DA Form 2404 and submit it to the next higher
level of maintenance.
NOTE
The terms ready/ available and mission capa-
ble refer to the same status: Generator set is on
hand and is able to perform its combat mis-
sions, refer to DA PAM 738-750.
2-5.6 Reporting and Correcting Deficiencies. If your
generator set does not perform as required, refer to Chap-
ter 3 under Troubleshooting for possible problems. Report
any malfunctions of failures on DA Form 2404, refer to
DA PAM 738-750.
2-5.7 Removal of Assemblies/Equipment to Perform
PMCS. There is no requirement to remove assemblies/
equipment prior to performing the PMCS.
2-9