2-20-5 Installation.
a. Insert panel light (1, FIGURE 2-11) into control panel.
b. Install washer (3) and nut (2).
c. Connect panel light electrical leads and remove tags.
d. Raise and secure control panel.
e. Connect negative battery cable. Close battery access door.
2-21 PRESS TO TEST LIGHTS.
2-21-1
a.
b.
2-21-2
a.
b.
c.
d.
e.
f.
g.
2-21-3
a.
b.
c.
d.
e.
f.
2-21-4
a.
b.
c.
d.
e.
2-52
Inspection.
Inspect lights for cracks, corrosion, evidence of shorting, and other damage.
Replace or repair Iights as necessary.
Testing.
Place MASTER SWITCH in either PRIME& RUN position.
Press in lamp holders (6, FIGURE 2-11) and check that lamps are lit.
If lamp (7) fails to light perform steps d through g.
Release control panel by turning two fasteners and lower control panel slowly.
Set multimeter for DC volts and check for voltage at terminals 1 and 3 on receptacle (10).
If voltage is present, replace press to test light assembly.
Raise and secure control panel.
Removal.
Shut down generator set.
Open battery access door and disconnect negative battery cable.
Release control panel by turning two fasteners and lower control panel slowly.
Tag and disconnect electrical leads to light receptacles (10, FIGURE 2-11).
Remove lamp holders (6), nuts (8), Iockwashers (9), and receptacles (10) from control panel.
If necessary, remove lamps (7) from lamp holders (6).
Install press to test light receptacles (10, FIGURE 2-11) in control panel with Iockwashers (9) and nuts (8).
If removed, install lamps (7) in lamp holders (6).
Install lamp holders (6) on receptacles (10).
Connect electrical leads and remove tags.
Raise and secure control panel.
Installation.