ARMY TM 9-6115-641-10
AIR FORCE TO 35C2-3-456-11
2-9 INITIAL ADJUSTMENTS. DAILY CHECKS AND
2-9.1
Perform all before (B)
2-4.
2-9.2
Initial Adjustments
PMCS, refer to TABLE
a
b.
c.
d.
e.
f.
Place DEAD CRANK switch in NORMAL position.
Push DC CONTROL POWER circuit breaker in.
Ensure AC voltage reconnection switch is
positioned to match voltage requirements.
Place AM-VM transfer switch in a position
corresponding to output terminal load connections,
refer to TABLE 2-1.
Pull out emergency stop switch.
Place PARALLEL UNIT switch in UNIT position.
2-9.3
Self Test
a. Place MASTER SWITCH to PRIME AND RUN
position.
b.
c.
d.
Push PRESS TO TEST pushbutton on malfunction
indicator panel. Ensure all indicator lights are Iii.
When PRESS TO TEST pushbutton is released, all
Iights should go out.
Press BATTLE SHORT press to test Iight on the
control panel assembly. Ensure indicator light is Iii.
When press to test light is released, light should go
out.
Press AC CIRCUIT INTERRUPTER press to test
light on the control panel assembly.
Ensure
indicator light is Iit. When press to test Iight is
released light should go out.
2-10
High voltage is produced when this
generator set is in operation. Personal
injury or death due to electrocution
could result.
2-20 Change 1