TM 5-6115-640-14&P
CHAPTER 6
TEST AND INSPECTION AFTER REPAIR
Section I. GENERAL REQUIREMENTS
6-1. GENERAL REQUIREMENTS .
The activity performing the repair is responsible for the performance of all applicable tests and inspections specified in
the technical manuals referenced below. Activities performing maintenance on any component of the power plants must
perform those tests and inspections required by the applicable component or system repair instruction.
Section II. INSPECTION
6-2. GENERATOR SET INSPECTIONS.
Refer to TM 5-6115-615-12 and -34 for inspections required following repair of the generator set.
6-3. TRAILER INSPECTIONS.
Refer to TM 9-2330-202-14&P for inspections required following. repair of the trailer.
Section III. OPERATIONAL TESTS
6-4. GENERATOR SET OPERATIONAL TESTS.
Refer to TM 5-6116-615-12 and -34 for operational tests required to verify satisfactory performance of the generator set.
6-5. TRAILER OPERATIONAL TESTS.
Refer to TM 9-2330-202-14&P for operational tests required to verify satisfactory performance of the trailer.
6-1/(6-2 blank)