TM 5-6115-629-14&P
Table 4-7. Unit Preventive Maintenance Checks and Services (PMCS). CONT.
H - Hours of operation W - Weekly
M Monthly S Seminally
A Annually
(As indicated)
(40 hours)
(100 hours)
(500 hours)
(1000 hours)
Interval
Item
Item to be
no.
H
Inspected
W
M
S
A
Procedures
25
l
Hydraulic Brake
Inspect for dents, cracks, loose connections
Hoses and Fittings
and leaks.
26
l
Air Hoses and
Inspect for dents, cracks, loose connections
Fittings
and leaks.
27
l
Brake Master
Check fluid level. Fill to 1/2 inch from
top.
28
l
Trailer Road Test
Perform road test paying special attention
to items that were repaired or adjusted,
in accordance with TM 9-2330-205-14&P.
Section VI.
TROUBLESHOOTING
4-13. General.
Troubleshooting procedures for components unique to the power plant end item are
given in paragraph 4-14. Troubleshooting information for the individual generator sets and trailers are
contained in their respective manuals referenced below:
a.
Generator Set Troubleshooting.
Refer to TM 5-6115-545-12 for troubleshooting procedures
applicable to the trailers.
b .
Trailer Troubleshooting.
Refer to TM 9-2330-205-14&P for troubleshooting procedures applicable
to the trailers.
4-14. Power Plant Troubleshooting.
Table 4-2 contains troubleshooting information for locating the
correcting operating troubles which may develop in components unique to the power plant end item.
Each malfunction is foIlowed by a list of tests or inspections which will help determine probable cause
and corrective actions to take.
Perform the tests/inspections and corrective actions in the order listed.
This manual cannot list all malfunctions that may occur, nor all tests or inspections and corrective
actions.
If a malfunction is not listed or cannot be corrected by listed corrective actions, notify your
supervisor.
* U.S. GOVERNMENT PRINTING OFFICE: 1989-754-029/ 00409
4-14
Change 1