Section IV. ORGANIZATIONAL MAINTENANCE INSTRUCTIONS
3-9. Transfer Switch Indicating Lights
a.
Removal. Remove the indicating lights as
illustrated in figure 3-8.
b.
Installation. Install the indicating lights as
illustrated in figure 3-8.
3-10. Ground Wires, Strap, and Terminal Stud
a.
Removal. Remove the ground strap, and wires
from the ground terminal stud and generator set as
shown in figure 3-3. Remove the terminal stud.
b.
Installation. Install the ground strap, wires and
terminal stud as shown in figure 3-3.
3-11. Tarpaulin, Roof Bows, and Leg Prop
a.
Removal.
(1)
Remove the tarpaulin from the unit.
(2)
Pull out the chain-secured pins that
secure the roof bows to the trailer bed and remove the
bows.
(3)
Remove the hardware that secures the leg
prop to the rear underside of the trailer bed and remove
the leg prop.
b.
Cleaning and Inspection.
(1)
Clean tarpaulin and bows with water and
detergent. Clean leg prop with approved cleaning
solvent. Dry thoroughly.
(2)
Inspect tarpaulin for tears, holes, broken
or missing ropes and straps, and other defects. Inspect
bows and leg prop for cracks, bends, and any other
defects.
c.
Installation.
(1)
Mount the leg prop to the underside of the
trailer bed and secure with mounting hardware.
(2)
Install the roof bows in the trailer bed and
secure with pins. Install the tarpaulin and secure in
desired position.
Section V. DIRECT AND GENERAL SUPPORT AND DEPOT
MAINTENANCE INSTRUCTIONS
3-12. Generator Transfer Switch
a.
Removal and Disassembly.
(1)
Tag and disconnect leads from the output
terminals to load.
(2)
Remove and disassemble the transfer
switch as illustrated in figure 3-8.
b.
Resassembly and Installation.
(1)
Reassemble and install the transfer switch
as illustrated in figure 3-8.
(2)
Connect load connections. (Refer to fig.
3-6).
3-13. Generator Sets
a.
Removal. Using figure 3-7 as a guide, perform
the following steps:
(1)
Disconnect fuel lines.
(2)
Disconnect electrical leads and load
cables.
(3)
Disconnect oil drain adapters.
(4)
Remove 2 bolts and 2 nuts that secure the
muffler pipe on the front generator set to the trailer.
(5)
Remove the 8 bolts that secure the two
generator sets to the trailer and remove the generator
sets.
b.
Installation. Using figure 3-7 as a guide, perform
the following steps:
(1)
Secure the 2 generator sets to the trailer
bed with 8 bolts.
(2)
Secure the front muffler pipe to trailer bed
with 2 bolts and 2 nuts.
Change 8 3-11