TM 11-6125-252-15
CHAPTER 7
PREPARATION OF EQUIPMENT FOR RESHIPMENT
Section I.
PREPARATION OF EQUIPMENT FOR RESHIPMENT
PU724/G. For stock numbers of materials, con-
7-1. General
sult SB 38100.
Quantity
Material
lined, corrugated paper carton. The preparations
Waterproof paper ------------------------- 10 Sq ft
for local shipment and for limited storage are the
Waterproof tape ------------------------ 15 ft
same.
Corrugated cardboard ------------------------- 30 sq ft
Gummed paper tape ---------------------- 30 ft
Plywood, 3/8 in. --------------- 71/2 in. x 15in.
72. Repackaging for Shipment or Limited
Storage
b. Packaging. The motor generator is to be
packaged as follows:
The exact procedure for repackaging depends on
the material available and the conditions under
(1) Mount unit on plywood base.
which the equipment is to be shipped or stored.
(2) Make inside carton to accept unit.
Secure all loose items and cables. Adapt the pro-
(3) Make filler and place filler and motor
cedures outlined below whenever possible. The
generator in inside carton.
information contained in the original packaging
(4) Wrap with waterproof paper and seal.
(5) Make outside carton to accept package
in (4) above.
a. Material Requirements. The following mate-
rials are required for packing Motor Generator
(6) Secure the wrap with gummed tape.
Section II deleted.
Change 2
7-1/(7-2 blank)