TM 9-6115-669-13&P
f.
Use the crane to lower power distribution unit (1, figure 4-30) all the way. Remove the crane
and sling.
g.
Install four screws (3), serrated lock washer (4), and washer (5). Tighten screws (3).
h. Bundle cables L3, N, and control cable J9 (14, 15, 16) under the bracket (17). Install bracket
(17) on pallet frame (18) using screws (11), serrated lock washer (12), and washer (13). Tighten
screws (11).
WARNING
Do not stand in the operating area of the crane. Do not walk
under the suspended load.
The lifting height of the crane must be sufficient to lift the
cable drum easily off the base frame.
NOTE
Be sure to identify the correct cable drum. Cable drum (4) has a bevel
on the drum.
i.
Install cable drum (4) as instructed in paragraph 4.11.
j.
Remove crane and sling.
k. Reconnect power cables and control cables to both Generator Sets 150 kW as instructed in
paragraph 4.17.
l.
Reconnect cables on power distribution unit as instructed in paragraph 4.16.
4-73