4.11 POWER CABLE DRUM MOUNT MAINTENANCE.
This task covers:
a. Removal
b. Installation
General Mechanic s Tool Kit
(item 2, appendix B)
Automotive Fuel and Electrical System Repair, Tool
Kit (item 3, appendix B)
Reference
Generator Set 150 kW shut
down, paragraph 2.8.1.
Lubricating grease
(item 1, appendix E)
Two
Never attempt to disconnect power cables while the Generator
Set 150 kW is running. Failure to observe this warning could
result in severe personal injury or death by electrocution.
NOTE
Before performing the removal operation below, the cable must be
completely wound up.
a.
Swing cable drum (1, figure 4-14) forward into operating position and lock in place.
CAUTION
Sling must be installed under cable retaining arm (11) to avoid damage to
arm while lifting.
b.
Position crane centered above cable drum (2) and lay sling (3) around the cable drum, loop
through, and suspend from the crane.
NOTE
The screws (4) cannot be removed, because the cable is wound up.
c.
Loosen four screws (4) from plate (6).
d.
Remove cable drum (2) by lifting with a crane.
e.
Remove four screws (7), serrated lock washers (8), and washers (9), and remove mount (6) off
pallet frame (10).
4-27