TM5-6115-640-14&P
(b)
Slide one lockwasher (7) and terminal lug (9) on load terminal stud (8) and secure with lockwasher (7) and
nut (6).
(c)
Position cover (4) on switch box (5) and secure with 16 flat washers (3), lockwashers (2), and screws (1).
(3)
Removal (Ground Wire).
(a)
Remove 16 screws (1, figure 4-9), lockwashers (2) and flat washers (3) securing cover (4) to switch box (5)
and take cover off switch box.
(b)
Remove nut (6) and lockwasher (7) from load terminal (8) LO inside switch box.
(c)
Slide power cable ground (white) wire terminals (9) and switch box ground wire (10) off load terminal (8)
LO.
(d)
Remove remaining lockwasher (7) from load terminal.
(e)
Remove nut (11) and lockwasher (12) from AC GROUND terminal E2 (13) inside box. Remove ground
wire (10).
c.
Installation (Ground Wire).
(1)
Install switch box ground wire (10) on AC GROUND terminal E2 (13) and secure with lockwasher (12) and nut
(11).
(2)
Install remaining end of ground wire (10) on load terminal (8) LO. Install power cable (white) wire terminals (9)
on terminal LO and secure the three wires with lockwasher (7) and nut (6).
(3)
Position cover (4) on switch box (5) and secure with 16 flat washers (3), lockwashers (2) and screws (1).
4-34