1-8. Administrative Storage.
a. Army equipment placed in administrative storage will have preventive maintenance performed
in accordance with the PMCS tables before storage. When equipment is removed from
storage, PMCS will be performed to ensure operational readiness.
b. (F) For administrative storage procedures for Air Force equipment, refer to TO 35-1-4,
Processing and Inspection of Aerospace Ground Equipment for Storage and Shipment.
1-9.
Preparation for Shipment and Storage.
a. (A) Army Refer to TB 740-97-2.
b. (F) Air Force - Refer to TO 35-1-4 for component of end item generator sets and TO 38-1-5
for installed engine.
Section Il. DESCRIPTION AND DATA
1-10.
Description. Power Plant AN/MJQ-16 is made up of two Tactical Utility Generator Sets, DOD
Model MEP-002A, mounted on a single modified M103A3 trailer. These generator sets are air-
cooled, diesel engine-driven units, each with a load capacity of 5 KW at 60 Hz. The trailer is a two-
wheeled unit with a l-1/2-ton carrying capacity. The modifications to the basic trailer provide stow-
age for the accessories and all equipment necessary for mobile operation as well as providing a work
platform for the operator and maintenance personnel. Output from the power plant is applied to the
system or equipment being powered through a switch box. The AN/MJQ-16 is supplied with either a 4-
wire or a 5-wire configuration switch box. Figures 1-1 and 1-2 illustrate the power plant with the fitted
cover removed to show the generator sets.
Figure 1-1. Power Plant, Roadside Front, Three-Quarter View.
1-2