TM 5-6115-628-14&P
h.
i.
j.
k.
l.
m.
n.
o.
Stow any remaining authorized equipment in accessory box.
Secure fire extinguishers and fuel cans in their respective mounting brackets.
Close all doors on the generator set enclosures.
On each power unit, swing personnel platform up into traveling position and secure with two
platform anchor quick-release pins.
WARNING
Use care when releasing spring-loaded lower tube of leveling jacks. The lower
tube will return to retracted position with considerable force and can cause
injury.
Retract lower tubes of leveling jacks. Swing Ieveling jacks up, into traveling position and secure
with Iockpins.
Remove wheel chocks.
Attach power units to towing vehicles. Refer to TM9-2330-205-14&P.
Release trailer handbrakes on both power units.
4-4. Reinstallation After Movement. After movement to a new worksite, install power plant in
accordance with paragraph 4-2.
Section Ill. REPAIR PARTS, SPECIAL TOOLS, SPECIAL TEST, MEASUREMENT AND
DIAGNOSTIC EQUIPMENT (TMDE)
4-5. Tools and Equipment. There are no special tools or equipment required to maintain the
AN/MJQ-15 power plant.
4-6. Maintenance Repair Parts. Repair parts and equipment for maintenance of this power plant are
listed and illustrated in the repair parts and special tools list in Appendix D of this manual.
Section IV. LUBRICATION INSTRUCTIONS
4-7. General. Detailed instructions for the lubrication of the major components of the power plant are
contained in the applicable Lubrication Orders (LOs). Refer to DA Pam 25-30 to ensure that the latest
editions of the L.O.S are used. This section contains lubrication instructions that are not included in
the Lubrication Orders.
4-8. Generator Lubrication. Refer to LO 5-6115-464-12 for generator set Lubrication Order.
4-9. Trailer Assembly Lubrication.
a. Trailer Lubrication. Refer to TM 9-2330-205-14&P for trailer Lubrication Order.
b. Personnel Platform Lubrication. The personnel platform is a modification to the standard
M200A1 trailer and, as such, does not appear in the associated L.O. Lubricate the personnel
platform semiannually as follows:
4-8
PIN:
064446-004