Figure 4-4. External Fuel Line Connection.
Section II. MOVEMENT TO A NEW WORKSITE
4-3. Dismantling for Movement.
Because the power plant is designed to be mobile, a minimum amount of
effort is required to relocate to a new worksite. Procedures are as follows:
a.
a1.
b.
c.
d.
e.
f.
g.
Shut down generator set and position switches in off position.
Disconnect power plant from system or equipment being powered.
Disconnect ground cables between switch box and GROUND TERMINAL studs on both power units.
Roll up cables and store in accessory boxes.
Using slide hammer, remove ground rods. Disassemble, clean, and stow ground rods in accessory
boxes.
Disconnect power plant from external fuel sources, if applicable.
Disconnect ground wires between switch box and GROUND rod. Roll up ground wires and store in
accessory boxes.
Disconnect power cables from both power units and from switch box. Roll up cables and secure each
to roadside fender of respective power unit using straps provided.
Close switch box access door and cap connectors. Position switch box on curbside fender of power
unit B and secure with hardware provided.
Change 4
4-7