Table 3-1 Intermediate PMCS (cont.)
Total time required: 0.4
ITEM TO BE INSPECTED
Sequence
Work time
PROCEDURE
No.
(T/H)
MOUNTING:
4
Check for cleanliness, stability, and
loose or missing hardware.
ELECTRICAL CAPS:
5
0.1
When accessible, check the electrical
brush caps for seating. Do not re-
move, reek, or twist to inspect.
Use only a direct pressure to be
sure that the cap is fully seated.
CONNECTIONS:
6
0.1
Cheek connections at terminal board
and ac power connector and see
that they are clean, intact, and secure.
OPERATION:
`7
During operation be alert for signs of
malfunction such as excessive vibration,
overheating, or variations in output
voltage and frequency. Refer to the operational check in
Table 3-2. Periodic PMCS
Total time required: 0.5
Sequence
Work time
ITEM TO BE INSPECTED
No.
PROCEDURE
(T/H)
PUBLICATIONS:
1
0.1
Cheek to see that all publications perti-
nent to this equipment are on hand,
complete, and usable. Check DA Pam
310-4 for recent changes to publications.
MODIFICATIONS:
2
0.1
Check DA Pam 310-7 to see that all URGENT
MWO's have been applied, and that all
NORMAL MWO's have been scheduled.
INSTALLATION:
3
Check to see that the inverter is prop-
erly secured with safety wire attached.
SLIPRINGS:
4
0.1
Remove the ac end cover and inspect the
sliprings for excessive wear and pitting.
AC CONTACT BRUSHES:
0.1
5
When accessible, remove the ac contact
for wear, cracks, chips, and broken
flexible wire. Check brush holders and
springs for cleanliness and proper
tension. Refer inverter to direct
support maintenance for replacement.
3-2