REMOVAL - Continued
18. Remove two screws (Figure 1, Sheet 2, Item 28), washers (Figure 1, Sheet 2, Item 29), locknuts (Figure 1,
Sheet 2, Item 30), and clamps (Figure 1, Sheet 2, Item 31) and (Figure 1, Sheet 2, Item 32). Remove battery
cable 24A40 (Figure 1, Sheet 2, Item 14).
19. Disconnect battery cable 2A40 from upper portion of starter (Figure 1, Sheet 2, Item 22) (Figure 1, Sheet 2,
Item 34) and battery cable 2C40 from lower portion of starter (Figure 1, Sheet 1, Item 33) (Figure 1, Sheet 2,
Item 34).
20. Disconnect battery cable 2C40 (Figure 1, Sheet 1, Item 33) from load terminal board GND terminal
21. Removed screw (Figure 1, Sheet 2, Item 35), washer (Figure 1, Sheet 2, Item 36), locknut (Figure 1, Sheet 2,
Item 37), and clamp (Figure 1, Sheet 2, Item 38). Remove battery cable 2C40 (Figure 1, Sheet 1, Item 33).
END OF TASK
INSTALLATION
NOTE
Install tiedown straps as required.
1. Install battery cable 2C40 (Figure 1, Sheet 1, Item 33) and secure with screw (Figure 1, Sheet 2, Item 35),
washer (Figure 1, Sheet 2, Item 36), clamp (Figure 1, Sheet 2, Item 38), and locknut (Figure 1, Sheet 2,
Item 37).
2. Connect battery cable 2C40 (Figure 1, Sheet 1, Item 33) to load terminal board terminal GND (WP 0046).
3. Install battery cable 2A40 (Figure 1, Sheet 2, Item 22) and connect battery cable 2A40 (Figure 1, Sheet 2,
Item 22) and battery cable 2C40 (Figure 1, Sheet 1, Item 30) to starter (Figure 1, Sheet 2, Item 34).
4. Install battery cable 24A40 (Figure 1, Sheet 2, Item 14), with two screws (Figure 1, Sheet 2, Item 28), washer
(Figure 1, Sheet 2, Item 29), locknut (Figure 1, Sheet 2, Item 30), and clamps (Figure 1, Sheet 2, Item 31) and
(Figure 1, Sheet 2, Item 32).
5. Connect battery cable 24A40 (Figure 1, Sheet 2, Item 14) to starter solenoid (Figure 1, Sheet 1, Item 27).
6. Position battery disconnect switch (Figure 1, Sheet 1, Item 23) near where it is to be installed. Remove tags
and connect battery cable 2A40 (Figure 1, Sheet 1, Item 22) and sensor cable 1A40 (Figure 1, Sheet 1,
Item 2).
7. Install battery disconnect switch (Figure 1, Sheet 1, Item 23) with four washers (Figure 1, Sheet 1, Item 26),
lockwashers (Figure 1, Sheet 1, Item 25), and screws (Figure 1, Sheet 1, Item 24).
8. Install battery cables 1D40 (Figure 1, Sheet 1, Item 4) and 24H40 (Figure 1, Sheet 1, Item 16) and connect to
slave receptacle SR (Figure 1, Sheet 1, Item 21).
9. Push slave receptacle SR (Figure 1, Sheet 1, Item 21) into TQG and install four washers (Figure 1, Sheet 1,
Item 20), screws (Figure 1, Sheet 1, Item 19), and nuts (Figure 1, Sheet 1, Item 18).
10. Install battery cable 24B40 (Figure 1, Sheet 1, Item 13) and connect battery cables 24B40 and 24H40
(Figure 1, Sheet 1, Item 16) to battery BT3 positive terminal (Figure 1, Sheet 1, Item 17).
0047-5