ARMY TM 9-6115-671-14
AIR FORCE TO 35C2-3-446-32
MARINE CORPS TM 09249A/09246A-14
2-45
a. Start generator set, paragraph 2.11.1.
b. Lift cover on BATTLE SHORT switch (4, Figure 2-8), and place switch in ON position to operate
generator set under these emergency conditions.
2.24
NUCLEAR, BIOLOGICAL, AND CHEMICAL (NBC) DECONTAMINATION PROCEDURES. Refer to
FM 3-5, NBC Decontamination, for information on decontamination procedures. Specific procedures for
the generator set are as follows:
a. Control panel indicator sealing gaskets, rubber sleeves, rope draw cords at output terminal access ports,
control panel door gaskets, access door gaskets, rubber tubing and belts within the engine
compartment, coverings for electrical conduits, external water drain tubing, and retaining cords for
NATO SLAVE RECEPTACLE covers will absorb and retain chemical agents. Replacement of these
items is the recommended method of decontamination.
FIGURE 2-13. NATO SLAVE RECEPTACLE