TM 9-6115-669-13&P
5.12 ELECTRONIC MODULE Al ASSEMBLY MAINTENANCE.
This task covers:
a.
Removal
b.
Inspection
c. Test
b.
Repair
e.
Installation
General Mechanics Tool Bit
(item 2, appendix B)
Automotive Fuel and Electrical System Repair,
Tool Bit (item 3, appendix B)
Reference
Shut down Generator Set
150 kW, paragraph 2.8.1.
Solder (item 7, appendix E)
Two
WARNING
The Generator Sets 150 kW produce lethal voltages.
Turn off power to the EPP III or Generator Set 150 kW before
performing any installation, ,removal, disassembly, or
assembly work
Wear protective gloves when performing any work on main
assemblies of the EPP III.
CAUTION
Label all cables before removing electrical or electronic assemblies or
components.
a.
Remove stanchion by PDU (1, figure 5-13).
b.
Open access door (2) and secure with prop (3).
c. Install stanchion.
d.
Record labeling and position of cables 116, 117, and 118 from K3 contactor and remove cables.
Refer to paragraph 5.10.
e.
Record labeling and position of cables and remove cables from electronic module A1 (8).
f.
Push in tab on bottom of electronic module A1 (8) and lift out electronic module.
5-35