TM 5-6115-640-14&P
4-12. REPORTING DEFICIENCIES.
If you discover any problem with the equipment during PMCS that you are unable to correct, it must be reported. Refer
to DA Pam 738-75u and report the deficiency using the proper forms.
Table 4-1. Unit Preventive Maintenance Checks and Services - Continued
H - Hours of operation
W - Weekly
M - Monthly
S - Semiannually
(As indicated)
(40 hours)
(100 hours)
(500 hours)
INTERVAL
ITEM
Item to be inspected
Procedures
NO.
H
W
M
S
WARNING
Before performing any maintenance
that requires climbing on or under
trailer, set trailer handbrakes, chock
wheels, and lower rear leg prop.
Injury to personnel could result
from trailer suddenly rolling or
tipping.
NOTE
Generator set checks and services
in this table are described as
performed on a single generator set.
These
procedures
must
be
performed on each of the two
generator sets that make up the
AN/MIQ-32 and AN/MJQ-33.
4-13